Minn. R. 7855.0300

Current through Register Vol. 48, No. 51, June 17, 2024
Part 7855.0300 - PROPOSED FUEL CONVERSION FACILITY; DESCRIPTION

Each application for a fuel conversion facility shall contain the following information:

A. a physical description of the facility, including:
(1) its location, to the fullest extent known;
(2) an estimate of the required land area and the height of the tallest structures;
(3) its design capacity in tons per hour of input material;
(4) a schematic drawing showing major components of the facility; and
(5) a map showing the planned location of the facility and its interconnections with energy transportation systems;
B. data regarding design and construction of the facility, including:
(1) if known, the complete name and business address of the engineer and firm that would be responsible for the design of the facility;
(2) if known, the complete name and business address of the company that would construct the facility;
(3) the proposed date for commencing construction and the proposed in-service date;
(4) the estimated installed cost of the facility in current dollars; and
(5) the estimated economic life of the facility; and
C. data regarding operation of the facility, including:
(1) a narrative description of the steps of the process;
(2) the types and sources of input materials that would be processed by the facility and the estimated energy content of each in Btu per appropriate unit of measure;
(3) the types of output products, the amount of each, and the estimated energy content of each in Btu per appropriate unit of measure;
(4) the projected annual operating and maintenance costs in current dollars for each of the first five calendar years of operation;
(5) a description of the methods that would be used to transport input and output materials to and from the facility;
(6) the estimated amounts and types of energy products that would be consumed during operation at the design capacity;
(7) the expected average percentage of use of the full design capacity for each of the first five calendar years of operation; and
(8) a discussion of the maintenance requirements of the facility, including the estimated impact on production.

Minn. R. 7855.0300

L 1983 c 289 s 115

Statutory Authority: MS s 216B.08; 216B.2421; 216B.243; 216C.10