Part 7852.3900 - PIPELINE CONSTRUCTION COMPLETION CERTIFICATION

Permittees shall file with the commission a written certification that the permitted pipeline construction has been completed in compliance with all permit conditions. The certification shall be considered by the commission within 60 days of its filing. The commission shall accept or reject the certification of completion and make a final determination regarding cost or reimbursements due. If the commission rejects the certification, it shall inform the permittee in writing which deficiencies, if corrected, will allow the certification to be accepted. When corrections to the deficiencies are completed, the permittee shall notify the commission, and the commission shall reconsider the certification at its next regularly scheduled meeting, provided the notification is received at least 20 days before the meeting. After acceptance of the certification by the commission, the commission's jurisdiction over the permittee's pipeline routing permit shall be terminated.

Minn. R. 7852.3900

13 SR 2046; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116I.015; 216G.02