Part 7852.1500 - ALTERNATIVE ROUTE ANALYSIS

A comparative environmental analysis of all of the pipeline routes accepted for consideration at public hearings shall be prepared by the commission staff or by the applicant and reviewed by the commission staff. This comparative environmental analysis must be submitted as prefiled testimony as required by part 1405.1900.

Minn. R. 7852.1500

13 SR 2046; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116I.015; 216G.02