A comparative environmental analysis of all of the pipeline routes accepted for consideration at public hearings shall be prepared by the commission staff or by the applicant and reviewed by the commission staff. This comparative environmental analysis must be submitted as prefiled testimony as required by part 1405.1900.
Minn. R. agency 138, ch. 7852, PIPELINE ROUTE SELECTION PROCEDURES, pt. 7852.1500
Statutory Authority: MS s 116I.015; 216G.02