A person submitting an application for a pipeline routing permit must comply with the application procedures of part 7852.2000 and submit an application that contains the information required in parts 7852.2100 to 7852.3100. Within nine months from commission acceptance of an application for route selection, unless the commission by resolution extends this deadline for cause, the commission shall issue a pipeline routing permit for the proposed pipeline and associated facilities.
Minn. R. agency 138, ch. 7852, PIPELINE ROUTE SELECTION PROCEDURES, pt. 7852.0800
Statutory Authority: MS s 116I.015; 216G.02