Minn. R. agency 138, ch. 7850, pt. 7850.2700

Current through Register Vol. 49, No. 20, November 12, 2024
Part 7850.2700 - FINAL DECISION
Subpart 1.Timing.

The commission shall make a final decision on a site permit or a route permit application within 60 days after receipt of the report of the administrative law judge. A final decision must be made within one year after the commission's determination that an application is complete. The commission may extend this time limit for up to three months for just cause or upon agreement of the applicant.

Subp. 2.EIS adequacy.

The commission shall not make a final decision on a permit until the commission has found the environmental impact statement to be adequate.

Subp. 3.Certificate of need decision.

The PUC shall not make a final decision on a permit for a project that requires a Certificate of Need from the Public Utilities Commission until the applicant has obtained the necessary approval.

Subp. 4.Notice.

The PUC shall publish notice of its final permit decision in the State Register within 30 days of the date the commission makes the decision. The PUC shall also publish notice in the EQB Monitor. The PUC shall mail notice of its final permit decision to those persons whose names are on the project contact list. The PUC shall post notice of the final decision on the agency's Web page, if possible.

Minn. R. agency 138, ch. 7850, pt. 7850.2700

27 SR 1295; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116C.66; 216E.16