Part 7850.1200 - APPLICABILITY

Parts 7850.1000 to 7850.5600 establish the requirements for the processing of permit applications by the Public Utilities Commission for large electric power generating plants and high voltage transmission lines. Requirements for environmental review of such projects before the commission are established in the applicable requirements of chapter 4410 and parts 7849.1000 to 7849.2100.

Minn. R. agency 138, ch. 7850, pt. 7850.1200

27 SR 1295; L 2005 c 97 art 3 s 19