Minn. R. 7849.0300

Current through Register Vol. 48, No. 51, June 17, 2024
Part 7849.0300 - CONSEQUENCES OF DELAY

The applicant shall present a discussion of anticipated consequences to its system, neighboring systems, and the power pool should the proposed facility be delayed one, two, and three years, or postponed indefinitely. This information must be provided for the following three levels of demand: the expected demand provided in response to part 7849.0270, subpart 2, and the upper and lower confidence levels provided in response to part 7849.0270, subpart 3, item E.

Minn. R. 7849.0300

L 1983 c 289 s 115; 12 SR 2624

Statutory Authority: MS s 216A.05; 216B.08; 216B.2421; 216B.243; 216C.10