Within 15 days of receiving payment under part 7835.4300, the utility with which the qualifying facility is interconnected must send the qualifying facility the payment it has received less the total charges it has incurred under part 7835.4200 and its own reasonable wheeling costs.
Minn. R. 7835.4400
Statutory Authority: MS s 216A.05; 216B.08; 216B.164