Part 7835.4019 - QUALIFYING FACILITIES OF 1,000 KILOWATT CAPACITY OR MORE

A qualifying facility with capacity of 1,000 kilowatt capacity or more must negotiate a contract with the public utility to set the applicable rates for payments to the customer of avoided capacity and energy costs. Nothing in parts 7835.4010 to 7835.4015 prevents a utility from connecting qualifying facilities of greater than 1,000 kilowatt capacity under its avoided cost rates.