Minn. R. 7690.1000

Current through Register Vol. 48, No. 51, June 17, 2024
Part 7690.1000 - PROPOSED DECISION
Subpart 1.Prepared by staff.

After reviewing the comments submitted under part 7690.0900, the department staff shall prepare a proposed decision approving, disapproving, or modifying a program, project, or evaluation plan. The proposed decision must be issued no later than 30 days after the reply comments described in part 7690.0900 are due.

Subp. 2.Copies sent.

The department staff shall serve a copy of its proposed decision on the utility, on any person who submitted a comment under part 7690.0900, and on all other persons the department believes are interested in the public utility's conservation improvement program.

Subp. 3.Comment period.

The department shall allow 15 days from the date the proposed decision is issued for written comments on the proposed decision.

Minn. R. 7690.1000

14 SR 2193; 22 SR 1402

Statutory Authority: MS s 216B.241