Minn. R. 2890.2600

Current through Register Vol. 48, No. 51, June 17, 2024
Part 2890.2600 - MAXIMUM COSTS FOR MOBILIZATION/DEMOBILIZATION (HEAVY EQUIPMENT), SAW-CUTTING, SOIL DISPOSAL, SURFACE REMOVAL, AND SURFACE REPLACEMENT

For a task listed in this part, the cost is prima facie unreasonable when it exceeds the amount specified for it in the bid for contractor services or the maximum cost specified for it in this part when the task was started, whichever is less.

A. Mobilization/demobilization (heavy equipment), including crew and equipment.

EquipmentMaximum cost
Dozer, loader, backhoe, or excavator, 70-250 hp. (0 to 50 miles one way)$218 each
Dozer, loader, backhoe, or excavator, over 250 hp. (0 to 50 miles one way)$327 each

B. Saw-cutting.

Surfacing materialMaximum cost
Asphalt$1.52 per linear foot
Concrete$4.36 per linear foot

C. Soil disposal.

VolumeMaximum cost
0 to 10 cubic yards$605
11 to 150 cubic yards$605 or $48 per cubic yard, whichever is greater
151 to 500 cubic yards$7,260 or $43 per cubic yard, whichever is greater
more than 500 cubic yards$21,175 or $36 per cubic yard, whichever is greater

D. Surface removal.

Surfacing materialMaximum cost
Asphalt$4.96 per square yard
Concrete (mesh-reinforced)$12 per square yard
Concrete (rod-reinforced)$15 per square yard

E. Surface replacement.

Surfacing materialMaximum cost
2-inch asphalt (including compacted gravel base)$2.42 per square foot
4-inch asphalt (including compacted gravel base)$4.84 per square foot
6-inch reinforced concrete (including a minimum of 4-inch compacted gravel base, forms, concrete in place, finish, and cure)$8 per square foot
8-inch reinforced concrete (including a minimum of 4-inch compacted gravel base, forms, concrete in place, finish, and cure)$10 per square foot

Minn. R. 2890.2600

20 SR 227; 28 SR 383; L 2010 c 241 s 4; MS s 115C.07 subd 3 paragraph (f)

Statutory Authority: MS s 115C.07