Mich. Admin. Code R. 209.55

Current through Vol. 24-19, November 1, 2024
Section R. 209.55 - Notification certification of date of project completion; filing of final cost

Rule 55.

(1) The holder of an industrial facilities exemption certificate shall notify the assessing officer of the local unit and the commission of the date of completion and final investment cost of a project.
(2) The notification of completion shall be in writing and shall be within 30 days of completion.
(3) The final cost of the project shall be in writing and shall be filed with the assessing officer and the commission within 90 days after completion.

Mich. Admin. Code R. 209.55

1982 AACS; 2009 AACS