Mich. Admin. Code R. 460.3501

Current through Vol. 24-10, June 15, 2024
Section R. 460.3501 - Electric plant; construction, installation, maintenance, and operation pursuant to good engineering practice required

Rule 501. The electric plant of an electric utility or cooperative must be constructed, installed, maintained, and operated pursuant to accepted good engineering practice in the electric industry to ensure, as far as reasonably possible, continuity of service, uniformity in the quality of service furnished, and the safety of persons and property.

Mich. Admin. Code R. 460.3501

1983 AACS; 2023 MR 7, Eff. 4/10/2023