Mich. Admin. Code R. 460.991

Current through Vol. 24-21, December 1, 2024
Section R. 460.991 - Business day exclusions

Rule 91. An electric utility shall notify the commission and all applicants that have in-process applications when timelines are being extended due to a business day where electric service is interrupted for 10% or more of an electric utility's customers, pursuant to R 460.901a(k). The electric utility shall also notify the commission and all applicants that have in-process applications when application processing resumes.

Mich. Admin. Code R. 460.991

2023 MR 8, Eff. 4/25/2023