Mich. Admin. Code R. 460.966

Current through Vol. 24-21, December 1, 2024
Section R. 460.966 - Inspection, testing, and commissioning

Rule 66.

(1) If the interconnection application requires telecommunications, cybersecurity, data exchange or remote controls operation, successful testing and certification of these items must be completed prior to or during testing. The electric utility's interconnection procedures must describe the technical requirements of common items, but site-specific requirements may be included in the interconnection agreement.
(2) An applicant shall notify the electric utility when installation of a DER and any required local code inspection and approval is complete. The applicant shall provide any test reports or configuration documents as defined in the standard level 1, 2, and 3 interconnection agreement or level 4 and 5 interconnection agreement.
(3) The electric utility shall review the applicant's inspection, test reports, or configuration documents, and communicate its intent to perform a witness or commissioning test, or waive its right to perform a witness test and commissioning test within 10 business days. If the electric utility finds the applicant's inspection, test reports, or configuration documents to be incomplete, insufficient, or unsatisfactory, the electric utility shall provide the reasons for doing so in writing and the applicant shall have not less than 20 business days or a mutually agreed upon timeframe with the utility to implement corrections to those documents. The applicant, after taking corrective action, shall request the electric utility to reconsider the inspection, test reports, or configuration documents.
(4) Subsequent to completion of the items in subrule (3), if the electric utility intends to witness or perform commissioning tests required to comply with the interconnection agreement or the interconnection procedures and inspect the DER, the electric utility shall witness or perform the commissioning tests and inspect the DER within the following:
(a) Ten business days of receiving the notification from the applicant pursuant to completion of subrules (2) and (3) of this rule for level 1 applications.
(b) Twenty business days after receiving the notification from the applicant pursuant to completion of subrules (2) and (3) of this rule for level 2 and level 3 applications.
(c) A mutually-agreed upon timeframe after receiving the notification from the applicant pursuant to completion of subrules (2) and (3) of this rule for level 4 and 5 applications.
(5) The electric utility may waive its right to visit the site and inspect the DER or perform the commissioning tests. The following requirements apply:
(a) If the electric utility waives this right, it shall provide a written waiver to the applicant within 10 business days from receiving the notification from the applicant pursuant to subrule (2) of this rule.
(b) The applicant shall provide the electric utility with the completed commissioning test report within 20 business days of receipt of the electric utility's written waiver.
(6) If the electric utility attempts to conduct the inspection and testing pursuant to subrule (4) of this rule at the arranged time and is unable to access the DER or complete the testing, the DER must remain disconnected until the applicant and the electric utility can complete the inspection and testing.
(7) If the electric utility witnessed or performed commissioning tests and inspected the DER pursuant to subrule (4) of this rule, within 5 business days of the receipt of the completed commissioning test report, the electric utility shall notify the applicant whether it has accepted or rejected the commissioning test report and found the site to be satisfactory or unsatisfactory. The following requirements apply:
(a) If the commissioning test report is accepted and the site was found satisfactory, the electric utility shall provide the notification of acceptance in writing, and the interconnection application proceeds to R 460.968.
(b) If the electric utility rejects the commissioning test report or did not find the site satisfactory, the electric utility shall provide its reasons for doing so in writing and the applicant has not less than 20 business days to implement corrections. The applicant, after taking corrective action, shall request the electric utility to reconsider its findings. The applicant may be billed the actual cost of any re-inspections.
(8) If the electric utility waived its right to witness or perform commissioning tests and inspect the DER pursuant to subrule (5) of this rule, within 5 business days of the receipt of the completed commissioning test report, the electric utility shall notify the applicant whether it has accepted or rejected the commissioning test report. The following requirements apply:
(a) If the commissioning test report is accepted, the electric utility shall provide notification of acceptance, and the interconnection application proceeds to R 460.968.
(b) If the electric utility rejects the commissioning test report, the electric utility shall provide its reasons for doing so in writing and the applicant has not less than 20 business days to implement corrections. The applicant, after taking corrective action, may then request the electric utility to reconsider its findings.
(9) The cost of testing and inspection for applicants participating in an electric utility's distributed generation program, as described in part 3 of these rules, R 460.1001 to R 460.1026, are considered a cost of operating a distributed generation program and must be recovered pursuant to section 175(1) of the clean and renewable energy and energy waste reduction act, 2008 PA 295, MCL 460.1175.
(10) If the applicant does not notify the electric utility that the DER is installed and ready to test pursuant to subrule (2) of this rule, the electric utility may, in writing, query the status of the interconnection. If the applicant does not provide a written response within 10 business days or no progress is evident, the electric utility may consider the interconnection application withdrawn.

Mich. Admin. Code R. 460.966

2023 MR 8, Eff. 4/25/2023