Current through Vol. 24-21, December 1, 2024
Section R. 460.944 - Fast track applicabilityRule 44.
(1) Level 1, level 2, level 3, level 4 applications, and level 5 applications as large as 5 MWac in which the DER is not proposing to interconnect with the electric utility's high voltage distribution system are eligible for the fast track. Level 5 applications proposing to interconnect to a utility's distribution system at 4.8 kV or less are not eligible for the fast track. Projects using an acceptable method for limited export are eligible for fast track.(2) An applicant that is eligible for the fast track may forgo the fast track and proceed directly to the study track.(3) An applicant with an application that is outside the limitations specified in subrule (1) of this rule may petition the electric utility to have its application evaluated under fast track. The electric utility may approve or reject this request at its discretion.(4) In determining fast track eligibility, an electric utility may aggregate all proposed new generation on a site regardless of the existence of a shared point of common coupling or multiple points of common coupling.Mich. Admin. Code R. 460.944
2023 MR 8, Eff. 4/25/2023