Rule 11. These rules apply to all interconnection applications filed on or after the effective date of these rules. The electric utility shall complete work on any interconnection study agreement executed prior to the effective date of these rules, pursuant to the terms and conditions of that interconnection study agreement. Any new studies or other additional work must be completed pursuant to these rules. An electric utility or an alternative electric supplier shall not restrict access to interconnection for level 1, level 2, and level 3 DERs that are not participants in the legacy net metering or distributed generation programs.
Mich. Admin. Code R. 460.911