Current through Vol. 24-21, December 1, 2024
Section R. 460.752 - Proceedings for waivers and exceptionsRule 52.
(1) A petition for a waiver of a customer credit provision filed by an electric utility or cooperative must be handled as a contested case proceeding. The burden of going forward with a request for a waiver is on the electric utility or cooperative. To be timely, a petition for a waiver of a customer credit provision of these rules must be filed not more than 14 calendar days after conclusion of the outage giving rise to application of the customer credit provision.(2) A petition for any other waiver or exception may be granted by the commission without notice or hearing.Mich. Admin. Code R. 460.752
2004 AACS.; 2023 MR 7, Eff. 4/10/2023