Mich. Admin. Code R. 408.15771

Current through Vol. 24-21, December 1, 2024
Section R. 408.15771 - Freezing operations

Rule 5771.

(1) A frozen plug shall be allowed to set a minimum of 1 hour per inch of pipe diameter being frozen.
(2) When possible, a frozen plug shall be pressure-tested from above for a minimum of 5 minutes to a pressure which is more than the known wellhead pressure.
(3) Following the pressure test, all pressure shall be bled off the pipe above the frozen plug and observed for a minimum of 15 minutes before breaking out the pipe and installing a new valve.
(4) After installing the new valve, void space between the frozen plug and valve shall be filled with fluid.
(5) A frozen plug shall be allowed to thaw at a normal rate. Steam or hot water shall not be used to thaw a frozen plug.

Mich. Admin. Code R. 408.15771

1979 AC; 1989 AACS