Section R. 281.1308 - Project completion explained

Rule 8. Pursuant to the provisions of section 35(1)(a) of the act, completion of a new, reconstructed, enlarged, repaired, or altered dam occurs when all the work depicted on all approved drawings and all specification requirements have been accomplished and all permit conditions have been implemented before the expiration of a permit.