Md. Code Regs. 26.21.01.16

Current through Register Vol. 51, No. 22, November 1, 2024
Section 26.21.01.16 - Reclamation Schedule
A. The permittee shall begin reclamation activities required by this chapter as soon as practicable after mining starts, continuing concurrently with mineral extraction and, upon termination of mining, until the entire permit area is reclaimed.
B. If site conditions dictate that reclamation cannot begin until mineral extraction is terminated, the reasons for this delay shall be detailed in the mining and reclamation plan, and the reclamation shall begin within 30 days of the termination of mineral extraction.
C. The permittee shall complete reclamation in accordance with the mining and reclamation plan within 2 years after mineral extraction has terminated.
D. If reclamation cannot be successfully completed within 2 years after mineral extraction has been terminated, the permittee shall submit a written request to the Department providing:
(1) The reasons for the delay;
(2) A description of measures to stabilize affected land, prevent any pollution, and eliminate hazards to health and safety; and
(3) A written acknowledgement of the delay of the reclamation from the landowner if different from the permittee.

Md. Code Regs. 26.21.01.16