Md. Code Regs. 26.04.04.13

Current through Register Vol. 51, No. 12, June 14, 2024
Section 26.04.04.13 - Relocation During Construction
A. If it is necessary to relocate a well under construction in order to obtain sufficient yield or potable water or because of a well construction problem, the well driller may relocate the well construction site under authority of the original permit if:
(1) The new site meets the requirements of this chapter and the requirements of the Approving Authority; and
(2) The permittee provides a drawing of the new well location on the well completion report.
B. If the new well location is found to not meet the requirements of this chapter the well shall be abandoned in accordance with this chapter.

Md. Code Regs. 26.04.04.13

Regulations .13 amended effective 42:1 Md. R. 19, eff.1/15/2015