Md. Code Regs. 26.02.07.09

Current through Register Vol. 51, No. 22, November 1, 2024
Section 26.02.07.09 - Waste Disposal
A. Each owner or contractor engaged in a lead abatement project shall:
(1) Remove lead waste from the site of a lead abatement project not later than 48 hours after completing the cleanup; and
(2) Comply with applicable hazardous waste regulations.
B. Transport and Disposal. Each owner and contractor engaged in a lead abatement project shall transport and dispose of lead waste in a manner to prevent lead from becoming airborne.

Md. Code Regs. 26.02.07.09