Current through Register Vol. 51, No. 22, November 1, 2024
Section 21.10.04.03 - Review and Investigation of Contractor ClaimUpon receipt of a contractor's claim, the procurement officer:
A. Shall investigate and review the facts pertinent to the claim;B. May request additional information or substantiation through any appropriate procedure; andC. Unless clearly inappropriate, shall seek the advice of the Office of the Attorney General.Md. Code Regs. 21.10.04.03
Regulations .03 adopted effective January 9, 1989 (15:27 Md. R. 3138)