Md. Code Regs. 20.63.12.05

Current through Register Vol. 52, No. 1, January 10, 2025
Section 20.63.12.05 - CCA Termination
A. A CCA shall coordinate with each electric company, the transfer of customers back to SOS upon termination of the CCA in order to mitigate the impact to SOS procurement.
B. A CCA that transfers all customers to SOS shall be considered to be dissolved.
C. A CCA may not re-form unless it has followed the procedures established by this subtitle for establishing a new CCA.
D. A CCA may not recover from electric company customers or electric companies any stranded costs for electricity supply contracts entered into by the CCA or generation owned by the CCA.
E. A county shall make reasonable efforts to mitigate any electric company SOS procurement costs associated with transferring CCA customers back to SOS upon termination of a CCA.

Md. Code Regs. 20.63.12.05

Regulation .05 adopted effective 51:2 Md. R. 76, eff. 2/5/2024