Md. Code Regs. 20.62.02.09

Current through Register Vol. 51, No. 26, December 27, 2024
Section 20.62.02.09 - Utility Cost Recovery
A. An electric company shall receive full and timely cost recovery of program credit costs.
B. An electric company may not establish a separate surcharge, fee, or rate for recovery of any program costs, including credit and administrative costs.
C. An electric company may include program credit costs in existing rate adjustments for distribution rates or as a revenue or cost component for transmission or commodity rates as accepted by the Commission.

Md. Code Regs. 20.62.02.09

Regulations .09 adopted effective 43:14 Md. R. 781, eff. 7/18/2016