Section 20.50.03.04 - Information to Be Filed with the Commission
A. Special Contracts. Each utility shall file with the Commission a copy of each contract for service not covered by the utility's filed tariff.
B. Installation Rules. Each utility shall file with the Commission a copy of the utility's rules, if any, designed by the utility for the use of engineers, architects, electrical contractors, etc., covering meter and service installations.
C. Bill Forms. Each utility shall file with the Commission a sample of each type of customer bill form, which shall include the information normally shown on a customer's bill for service.
D. Map of System. Each utility shall file with the Commission a map showing the utility's operating area. This map shall be revised annually unless the revision is unnecessary, in which event the utility shall notify the Commission that the map on file is current. If practicable, the map should show:
(1) Generating stations;
(2) Transmission lines with voltages;
(3) Primary distribution lines;
(4) State boundary crossings; and
(5) Territorial boundary.
E. Persons to Contact. Each utility shall notify Commission staff, within 30 days of a change, of the name, title, address, telephone number, and email address of the person who should be contacted in connection with:
(1) General electric distribution management duties;
(2) Customer relations (complaints);
(3) Electric distribution operations;
(4) Electric distribution planning;
(5) Meter tests and repairs;
(6) Emergencies during non-office hours;
(7) Cybersecurity; and
(8) Regulatory contact for general inquiries.
F. Fatal Accident Notice. In the event of a fatal accident, prompt notice shall be given to the Commission by telephone or email.
G. Accident Notice. Each utility shall file with the Commission an "Accident Notice" report, on forms provided by the Commission, within 30 days after the end of any month during which an accident occurred.
H. Line Support Identification. Each utility shall file with the Commission a photograph or drawing showing the identifying symbol or symbols used to mark the utility's line supports.

Md. Code Regs. 20.50.03.04

Regulation .04 amended effective September 21, 2009 (36:19 Md. R. 1438)
Regulation .04H amended effective September 18, 1989 (16:18 Md. R. 2024); amended effective 46:24 Md. R. 1104, eff. 12/2/2019; amended effective 50:16 Md. R. 728, eff. 8/21/2023