65- 407 C.M.R. ch. 332, § 3

Current through 2024-25, June 19, 2024
Section 407-332-3 - EXEMPTIONS

The following are exempt from section 3133 and the requirements of this chapter:

A.Purchases from qualifying facilities. Purchases made by an electric utility from any cogenerator or small power producer, as defined in 35-A M.R.S.A. §3303;
B.Wholesale purchase extensions. Extensions of existing wholesale power purchase arrangements by consumer-;owned electric utilities, as defined in 35-A M.R.S.A. §3501, that are subject to Federal Energy Regulatory Commission review with respect to rates; and
C.Amendments of contracts not originally approved. Any amendment, extension or renewal of any contract otherwise subject to this chapter for which the original contract was not subject to approval by the Commission. The utility shall, however, file a copy of such amendments, extensions or renewals to the Commission within 7 days of the day when the utility receives notice of the proposal.