65- 407 C.M.R. ch. 317, § 2

Current through 2024-25, June 19, 2024
Section 407-317-2 - CREATION AND IMPLEMENTATION OF AMPs
A. Creation and Implementation of the AMPs

Each T&D Utility shall implement an AMP approved by the Commission by October 1, 2015.

B. Review and Approval by Commission

Each T&D Utility shall submit terms and conditions for its AMP pursuant to this Chapter by May 15, 2015. The AMPs are subject to Commission review and approval, which review and approval is delegated to the Director of the Consumer Assistance Division.

65- 407 C.M.R. ch. 317, § 2