18- 554 C.M.R. ch. 8, § 1

Current through 2024-50, December 11, 2024
Section 554-8-1 - Purpose and Scope

Summary: This section states the purpose and scope of the Bureau's rule establishing procedures for undertaking contracts using other than the traditional design-bid-build method for the construction of public improvements.

The purpose of this Chapter is to implement the Director's authority to establish procedures, in addition to those established by statute, for procuring and awarding contracts using alternative project delivery methods. This Chapter does not apply to the award of contracts for public improvements under the traditional design-bid-build method. The rules for public school construction using alternative project delivery methods are addressed separately.

18- 554 C.M.R. ch. 8, § 1

EFFECTIVE DATE:
December 31, 2006

STATUTORY AUTHORITY: 5 M.R.S.A. §1743