Section 170-19-IV - Employer Self-Monitoring and Reporting
A. A construction employer must demonstrate compliance with the statute by submitting to the Bureau a plan for locating and employing a sufficient number of qualified apprentices.
B. The plan must be submitted prior to starting the construction project or prior to starting each phase of the construction project.
C. When each phase of the construction project is completed, the employer must submit to the Bureau an interim report disclosing the results of its efforts to employ qualified apprentices including a clear explanation if they failed to hire a sufficient number of qualified apprentices during that phase of the project.
D. When the entire project is completed, the employer must submit a final report also including a clear explanation if they failed to hire a sufficient number of qualified apprentices during the entire project.