The information in this subsection must be submitted to the Department as part of a completed application for approval of a septage storage facility. Additional information may required by the Department to evaluate the application.
All storage sites must be operated in conformance with a Department-approved operating plan. The operating plan must include all information that would enable supervisory personnel, operating personnel, and persons evaluating the operation of the facility, to determine what sequence of operation, plans, diagrams, policies, procedures and legal requirements must be followed for orderly and successful operation on a daily and yearly basis. This plan must be updated as necessary to address operational changes.
06- 096 C.M.R. ch. 420, § 14