Current through 2024-44, October 30, 2024
Section 096-117-9 - Compliance ScheduleA. New Sources. The owner or operator of a new source with applicable requirements under this Chapter shall become compliant with this Chapter within 60 days of achieving maximum load or within 180 days of initial startup, whichever comes first. All audit and test results shall be submitted within 30 days following the audit/test unless prior approval is obtained by the Department and EPA.B. Existing Sources. For all other existing CEMS previously required by federal regulation, air emission license condition or consent agreement, an owner or operator subject to the requirements of this Chapter shall be in compliance with all of its applicable provisions within 60 days following the effective date of this regulation.06- 096 C.M.R. ch. 117, § 9