Final Funding Approval by the Commissioner establishes the Project Budget and takes place after construction bids have been received. At that time the Commissioner may reduce the budget to finance the project, thus providing additional funds for other projects. Expenditures from each line item shall not exceed the amount of that line item except as approved by the Facilities Team. The Commissioner's Certificate of Final Funding Approval will also specify the date of the bond sale for the project and the length of the bonding period.
The bid and project contingency funds of each project budget will only be expended with the approval of the Facilities Team.
When a line item of the Project Budget has surplus funds after all obligations have been met, the SAU shall not expend the surplus without the approval of the Facilities Team.
The SAU shall track the monthly expenditures and revenues of the project using the format provided by the Facilities Team. This information shall be submitted to the Facilities Team and compliance review staff for periodic review.
The Department shall have a representative for each project whose responsibility will include but not be limited to the following: attending monthly requisition meetings, monitoring construction progress, reviewing proposed change orders, conducting monthly reviews of financial statements and acting as a conduit to the Department's Director of School Facilities. The SAU may employ an Owner's Representative to meet the additional local needs of the project.