Section 041-13-2 - New Installations
A.Registration and Certification

Before any low pressure boiler is operated in the State of Maine, the owner of the low pressure boiler must register the low pressure boiler with the Board and must obtain a current, valid inspection certificate for the low pressure boiler.

B.Installation Inspections
(1)Notification. The owner of a low pressure boiler must notify the State and the owner's insurance company when applicable before placing a new low pressure boiler in service.
(2)Inspection. An Inspector must conduct the initial inspection of a low pressure boiler in accordance with the applicable code specified in Chapter 11 of these rules. The initial inspection must consist of an internal and external inspection, if construction permits. The Inspector must report the results of the inspection to the Board on forms provided by the Board.
C.Relocation. Before a relocated low pressure boiler is installed, the owner must petition the Chief Inspector for a variance to approve the installation. The Chief Inspector must perform the initial inspection of a relocated boiler.