Section 041-12-1 - New Installations
A.Approval of Installation. Before a power boiler is installed, the owner must submit to the Chief Inspector detailed plans and specifications of the installation for approval at least 30 days prior to installation on a form provided by the Board. The owner must comply with any request by the Chief Inspector for additional information. A power boiler may not be installed unless the Chief Inspector has issued a written approval for the installation. Emergency situations will be handled on a case by case basis by contacting the Chief Inspector.
B.Initial Inspections
(1)Inspection. The Chief Inspector shall conduct the initial inspection of a new or relocated power boiler in accordance with the applicable code(s) specified in Chapter 11 of these rules. The initial inspection must consist of an internal and external inspection, if construction permits. Additionally, a hydrostatic test must be completed of the entire boiler and boiler external piping after field installation. The Chief Inspector shall record and submit the results of the inspection to the Board.
(2)Interim Inspection Certificate. If after initial inspection the Chief Inspector determines that a power boiler complies with all provisions of Title 32, Chapter 131, the Board's rules, and the applicable national code(s), the Chief Inspector may issue an interim inspection certificate for the operation of the power boiler up to 60 days pending issuance of the initial inspection certificate.
(3)Expenses. The owner or the owner's designee must pay the initial inspection fee and any related expenses for the initial inspection of a power boiler. If the fee has not been paid by the date the interim certificate expires, the Chief Inspector shall direct the owner to suspend operation of the power boiler.
C.Approval of Operation. Before a newly installed power boiler is operated, the owner must comply with the provisions of Paragraphs A and B, and the Chief Inspector must approve the operation on a form provided by the Board.
D.Relocation. Before a relocated power boiler is installed, the owner must petition the Chief Inspector for a variance to approve the installation. A relocated boiler must meet the requirements for new installations, where practicable.