La. Admin. Code tit. 56 § III-2113

Current through Register Vol. 50, No. 11, November 20, 2024
Section III-2113 - Distribution of Funds
A. Funding. Program funds shall be distributed in accordance with the approved construction program. The funding for any single project that is submitted to the legislature for funding may be limited to a maximum legislative funding authority of $9 million. The department may increase the funding limit for a fiscal year based on the availability of funds. The department may consult with PAL regarding the limit; but, the final limit shall be at the sole discretion of the department.
i. The actual distribution of these funds to the ports for each approved project shall be at the sole discretion of the department. The department may consult with PAL in determining this distribution.
ii. The department may limit the funding distribution to each port authority to no more than one-third 1/3 per year of the single project maximum legislative funding authority established by the department for the fiscal year.
B. Construction. Should the funding level be insufficient to fund all the projects that have been recommended, then the unfunded projects will be included in the recommended list of projects the following year. An unfunded project may be included in the recommended list of projects up to four years without port authority re-submitting an application. If a reimbursement agreement has been executed with the department and the project has begun construction prior to the expiration of the four year period, then the project will remain on said list until all program funds have been authorized.
C. Cancellation. The department may cancel any project that is not under construction with the below mentioned time limits and any unexpected proceeds may be reallocated to another port project: (The award of a construction contract shall satisfy the requirement to be "under construction.")
1. for projects that are completely funded in one fiscal year, within 18 months of the date of notification from the secretary of the department or his designated representative, that the project has sufficient funding to be completed;
2. for projects that are completely funded over two fiscal years, within 12 months of the date of notification from the secretary of the department, or his designated representative, that the project has sufficient funding to be completed;
3. for projects that are completely funded over three or more fiscal years, within six months of the date of notification from the secretary of the department or his designated representative, that the project has sufficient funding to be completed;
4. for projects that have approval from the department to be divided into more than one construction contract, the above time frames apply to each independent contract that has sufficient funding to be completed. An independent contract shall be a contract that does not require the completion of another contract in order to be constructed. Each additional dependent contract shall be constructed within six months from completion of the contract that it is dependent upon;
5. if a port authority has a project that is eligible for cancellation under the provisions of this Section, the port shall not be eligible to submit an application for funding or to receive additional funding for previously recommended projects until the port authority officially withdraws its project, or until the project, including all approved phases, has been completed.

La. Admin. Code tit. 56, § III-2113

Promulgated by the Department of Transportation and Development, Division of Flood Control and Water Management, LR 18:759 (July 1992), repromulgated by the Department of Transportation and Development, Office of Public Works, LR 31:942 (April 2005), amended LR 34:1046 (June 2008), Amended by the Department of Transportation and Development, Office of Multimodal Commerce, LR 491444 (8/1/2023).
AUTHORITY NOTE: Promulgated in accordance with R.S. 34:3451-3463.