Current through Register Vol. 50, No. 11, November 20, 2024
Section XIII-6717 - Plans and Procedures [49 CFR 193.2017]A. Each operator shall maintain at each LNG plant the plans and procedures required for that plant by this part. The plans and procedures must be available upon request for review and inspection by the commissioner. In addition, each change to the plans or procedures must be available at the LNG plant for review and inspection within 20 days after the change is made. [ 49 CFR 193.2017(a) ]B. The associate administrator or the state agency that has submitted a current certification under the pipeline safety laws, ( 49 U.S.C. 60101 et seq.) with respect to the pipeline facility governed by an operator's plans and procedures may, after notice and opportunity for hearing as provided in 49 CFR 190.206 or the relevant state procedures, require the operator to amend its plans and procedures as necessary to provide a reasonable level of safety. [ 49 CFR 192.603(c) ]C. Each operator must review and update the plans and procedures required by this part: 1. when a component is changed significantly or a new component is installed; and [ 49 CFR 193.2017(c)(1) ]2. at intervals not exceeding 27 months, but at least once every two calendar years. [ 49 CFR 193.2017(c)(2) ]La. Admin. Code tit. 43, § XIII-6717
Promulgated by the Department of Natural Resources, Office of Conservation, LR 441049 (6/1/2018).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:551.C.