Current through Register Vol. 50, No. 9, September 20, 2024
Section XIII-2921 - Distribution Systems: Patrolling [49 CFR 192.721]A. The frequency of patrolling mains must be determined by the severity of the conditions which could cause failure or leakage, and the consequent hazards to public safety. [ 49 CFR 192.721(a)]B. Mains in places or on structures where anticipated physical movement or external loading could cause failure or leakage must be patrolled: [ 49 CFR 192.721(b) ] 1. in business districts, at intervals not exceeding 4 1/2 months, but at least four times each calendar year; and [ 49 CFR 192.721(b)(1)]2. outside business districts, at intervals not exceeding seven and one-half months, but at least twice each calendar year. [ 49 CFR 192.721(b)(2)]La. Admin. Code tit. 43, § XIII-2921
Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:245 (April 1983), amended LR 10:537 (July 1984), LR 24:1313 (July 1998), LR 30:1268 (June 2004).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.