Section XIII-2919 - Transmission Lines: Testing of Repairs [49 CFR 192.719]A. Testing of Replacement Pipe. If a segment of transmission line is repaired by cutting out the damaged portion of the pipe as a cylinder, the replacement pipe must be tested to the pressure required for a new line installed in the same location. This test may be made on the pipe before it is installed. [ 49 CFR 192.719(a)]B. Testing of Repairs Made by Welding. Each repair made by welding in accordance with §§2913, 2915, and 2917 must be examined in accordance with §1321 [ 49 CFR 192.719(b)]La. Admin. Code tit. 43, § XIII-2919
Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:245 (April 1983), amended LR 10:537 (July 1984), LR 30:1268 (June 2004).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.