Current through Register Vol. 50, No. 9, September 20, 2024
Section XIII-2906 - Transmission Lines: Leakage Surveys [49 CFR 192.706]A. Leakage surveys of a transmission line must be conducted at intervals not exceeding 15 months, but at least once each calendar year. However, in the case of a transmission line which transports gas in conformity with §2725 without an odor or odorant, leakage surveys using leak detector equipment must be conducted: [ 49 CFR 192.706] 1. in Class 3 locations, at intervals not exceeding seven and one-half months, but at least twice each calendar year; and [ 49 CFR 192.706(a)]2. in Class 4 locations, at intervals not exceeding four and one-half months, but at least four times each calendar year. [ 49 CFR 192.706(b)]La. Admin. Code tit. 43, § XIII-2906
Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:244 (April 1983), amended LR 10:536 (July 1984), LR:21:823 (August 1995), LR 30:1267 (June 2004).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.