La. Admin. Code tit. 43 § XIII-2731

Current through Register Vol. 50, No. 9, September 20, 2024
Section XIII-2731 - Control Room Management [49 CFR 192.631]
A. General [ 49 CFR 192.631(a)]
1. This Section applies to each operator of a pipeline facility with a controller working in a control room who monitors and controls all or part of a pipeline facility through a SCADA system. Each operator must have and follow written control room management procedures that implement the requirements of this Section, except that for each control room where an operator's activities are limited to either or both of: [ 49 CFR 192.631(a)(1)]
a. distribution with less than 250,000 services; or [ 49 CFR 192.631(a)(1)(i)]
b. transmission without a compressor station, the operator must have and follow written procedures that implement only Subsections D (regarding fatigue), I (regarding compliance validation), and J (regarding compliance and deviations) of this Section. [ 49 CFR 192.631(a)(1)(ii) ]
2. The procedures required by this Section must be integrated, as appropriate, with operating and emergency procedures required by §2705 An operator must develop the procedures no later than August 1, 2011, and must implement the procedures according to the following schedule. The procedures required by Subsections and Paragraphs B, C.5, D.2, D.3, F and G of this Section must be implemented no later than October 1, 2011. The procedures required by Paragraphs C.1 through C.4, D.1, D.4, and E must be implemented no later than August 1, 2012. The training procedures required by Subsection H must be implemented no later than August 1, 2012, except that any training required by another Paragraph of this Section must be implemented no later than the deadline for that Paragraph. [ 49 CFR 192.631(a)(2)]
B. Roles and responsibilities. Each operator must define the roles and responsibilities of a controller during normal, abnormal, and emergency operating conditions. To provide for a controller's prompt and appropriate response to operating conditions, an operator must define each of the following: [ 49 CFR 192.631(b)]
1. a controller's authority and responsibility to make decisions and take actions during normal operations; [ 49 CFR 192.631(b)(1)]
2. a controller's role when an abnormal operating condition is detected, even if the controller is not the first to detect the condition, including the controller's responsibility to take specific actions and to communicate with others; [ 49 CFR 192.631(b)(2)]
3. a controller's role during an emergency, even if the controller is not the first to detect the emergency, including the controller's responsibility to take specific actions and to communicate with others; [ 49 CFR 192.631(b)(3) ]
4. a method of recording controller shift-changes and any hand-over of responsibility between controllers; and [ 49 CFR 192.631(b)(4) ]
5. The roles, responsibilities and qualifications of others with the authority to direct or supersede the specific technical actions of a controller. [ 49 CFR 192.631(b)(5) ]
C. Provide Adequate Information. Each operator must provide its controllers with the information, tools, processes and procedures necessary for the controllers to carry out the roles and responsibilities the operator has defined by performing each of the following: [ 49 CFR 192.631(c)]
1. implement sections 1 1, and 11.3 of API RP 1165 (incorporated by reference, see §507) whenever a SCADA system is added, expanded or replaced, unless the operator demonstrates that certain provisions of sections 4 1, and 11.3 of API RP 1165 are not practical for the SCADA system used; [ 49 CFR 192.631(c)(1)]
2. conduct a point-to-point verification between SCADA displays and related field equipment when field equipment is added or moved and when other changes that affect pipeline safety are made to field equipment or SCADA displays; [ 49 CFR 192.631(c)(2)]
3. test and verify an internal communication plan to provide adequate means for manual operation of the pipeline safely, at least once each calendar year, but at intervals not to exceed 15 months; [ 49 CFR 192.631(c)(3)]
4. test any backup SCADA systems at least once each calendar year, but at intervals not to exceed 15 months; and [ 49 CFR 192.631(c)(4)]
5. establish and implement procedures for when a different controller assumes responsibility, including the content of information to be exchanged. [ 49 CFR 192.631(c)(5)]
D. Fatigue Mitigation. Each operator must implement the following methods to reduce the risk associated with controller fatigue that could inhibit a controller's ability to carry out the roles and responsibilities the operator has defined: [ 49 CFR 192.631(d)]
1. establish shift lengths and schedule rotations that provide controllers off-duty time sufficient to achieve eight hours of continuous sleep; [ 49 CFR 192.631(d)(1)]
2. educate controllers and supervisors in fatigue mitigation strategies and how off-duty activities contribute to fatigue; [ 49 CFR 192.631(d)(2)]
3. train controllers and supervisors to recognize the effects of fatigue; and [ 49 CFR 192.631(d)(3)]
4. establish a maximum limit on controller hours-of-service, which may provide for an emergency deviation from the maximum limit if necessary for the safe operation of a pipeline facility. [ 49 CFR 192.631(d)(4)]
E. Alarm Management. Each operator using a SCADA system must have a written alarm management plan to provide for effective controller response to alarms. An operator's plan must include provisions to: [ 49 CFR 192.631(e)]
1. review SCADA safety-related alarm operations using a process that ensures alarms are accurate and support safe pipeline operations; [ 49 CFR 192.631(e)(1) ]
2. identify at least once each calendar month points affecting safety that have been taken off scan in the SCADA host, have had alarms inhibited, generated false alarms, or that have had forced or manual values for periods of time exceeding that required for associated maintenance or operating activities; [ 49 CFR 192.631(e)(2)]
3. verify the correct safety-related alarm set-point values and alarm descriptions at least once each calendar year, but at intervals not to exceed 15 months; [ 49 CFR 192.631(e)(3)]
4. review the alarm management plan required by this paragraph at least once each calendar year, but at intervals not exceeding 15 months, to determine the effectiveness of the plan; [ 49 CFR 192.631(e)(4)]
5. monitor the content and volume of general activity being directed to and required of each controller at least once each calendar year, but at intervals not to exceed 15 months, that will assure controllers have sufficient time to analyze and react to incoming alarms; and [ 49 CFR 192.631(e)(5)]
6. address deficiencies identified through the implementation of Paragraphs E.1 through E.5 of this Section. [ 49 CFR 192.631(e)(6)]
F. Change Management. Each operator must assure that changes that could affect control room operations are coordinated with the control room personnel by performing each of the following: [ 49 CFR 192.631(f)]
1. establish communications between control room representatives, operator's management, and associated field personnel when planning and implementing physical changes to pipeline equipment or configuration; [ 49 CFR 192.631(f)(1)]
2. require its field personnel to contact the control room when emergency conditions exist and when making field changes that affect control room operations; and [ 49 CFR 192.631(f)(2)]
3. seek control room or control room management participation in planning prior to implementation of significant pipeline hydraulic or configuration changes. [ 49 CFR 192.631(f)(3)]
G. Operating Experience. Each operator must assure that lessons learned from its operating experience are incorporated, as appropriate, into its control room management procedures by performing each of the following: [ 49 CFR 192.631(g)]
1. review incidents that must be reported pursuant to Subpart 2 of this Part to determine if control room actions contributed to the event and, if so, correct, where necessary, deficiencies related to: [ 49 CFR 192.631(g)(1)]
a. controller fatigue; [ 49 CFR 192.631(g)(1)(i)]
b. field equipment; [ 49 CFR 192.631(g)(1)(ii) ]
c. the operation of any relief device; [ 49 CFR 192.631(g)(1)(iii) ]
d. procedures; [ 49 CFR 192.631(g)(1)(iv) ]
e. SCADA system configuration; and [ 49 CFR 192.631(g)(1)(v)]
f. SCADA system performance; [ 49 CFR 192.631(g)(1)(vi) ]
2. include lessons learned from the operator's experience in the training program required by this Section. [ 49 CFR 192.631(g)(2)]
H. Training. Each operator must establish a controller training program and review the training program content to identify potential improvements at least once each calendar year, but at intervals not to exceed 15 months. An operator's program must provide for training each controller to carry out the roles and responsibilities defined by the operator. In addition, the training program must include the following elements: [ 49 CFR 192.631(h)]
1. responding to abnormal operating conditions likely to occur simultaneously or in sequence; [ 49 CFR 192.631(h)(1)]
2. use of a computerized simulator or non-computerized (tabletop) method for training controllers to recognize abnormal operating conditions; [ 49 CFR 192.631(h)(2)]
3. training controllers on their responsibilities for communication under the operator's emergency response procedures; [ 49 CFR 192.631(h)(3)]
4. training that will provide a controller a working knowledge of the pipeline system, especially during the development of abnormal operating conditions; [ 49 CFR 192.631(h)(4) ]
5. for pipeline operating setups that are periodically, but infrequently used, providing an opportunity for controllers to review relevant procedures in advance of their application; [ 49 CFR 192.631(h)(5) ]
6. Control room team training and exercises that include both controllers and other individuals, defined by the operator, who would reasonably be expected to operationally collaborate with controllers (control room personnel) during normal, abnormal or emergency situations. Operators must comply with the team training requirements under this paragraph by no later than January 23, 2018. [ 49 CFR 192.631(h)(6) ]
I. Compliance Validation. Upon request, operators must submit their procedures to PHMSA or, in the case of an intrastate pipeline facility regulated by a state, to the appropriate state agency. [ 49 CFR 192.631(i)]
J. Compliance and Deviations. An operator must maintain for review during inspection: [ 49 CFR 192.631(j)]
1. records that demonstrate compliance with the requirements of this Section; and [ 49 CFR 192.631(j)(1)]
2. documentation to demonstrate that any deviation from the procedures required by this Section was necessary for the safe operation of a pipeline facility. [ 49 CFR 192.631(j)(2)]

La. Admin. Code tit. 43, § XIII-2731

Promulgated by the Department of Natural Resources, Office of Conservation, LR 38:119 (January 2012), Amended LR 441041 (6/1/2018).
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.