Table 1 to Subparagraph A.2.b | ||||
Factors1, Segment | ||||
Class Location | Installed before (Nov. 12, 1970) | Installed after (Nov. 11, 1970) and before July 1, 2020 | Installed on or after July 1, 2020 | Converted under CFR §192.14 |
1 | 1.1 | 1.1 | 1.25 | 1.25 |
2 | 1.25 | 1.25 | 1.25 | 1.25 |
3 | 1.4 | 1.5 | 1.5 | 1.5 |
4 | 1.4 | 1.5 | 1.5 | 1.5 |
1For offshore segments installed, uprated or converted after July 31, 1977, that are not located on an offshore platform, the factor is 1.25. For segments installed, uprated or converted after July 31, 1977, that are located on an offshore platform or on a platform in inland navigable waters, including a pipe riser, the factor is 1.5.
2For a component with a design pressure established in accordance with §1113.A or B installed after July 14, 2004, the factor is 1.3.
Pipeline Segment | Pressure Date | Test Date |
-Onshore gathering line that first became subject to this Subpart (other than §2712) after April 13, 2006. | March 15, 2006, or date line becomes subject to this Subpart, whichever is later. | 5 years preceding applicable date in second column. |
Onshore regulated gathering pipeline (Type C under §509.D that first became subject to this part (other than §2712) on or after May 16, 2022 | May 16, 2023, or date pipeline becomes subject to this Subpart, whichever is later | 5 years preceding applicable date in second column. |
-Onshore transmission line that was a gathering line not subject to this Subpart before March 15, 2006. | March 15, 2006, or date line becomes subject to this Subpart, whichever is later. | 5 years preceding applicable date in second column |
Offshore gathering lines. | July 1, 1976 | July 1, 1971 |
All other pipelines. | July 1, 1970 | July 1, 1965 |
La. Admin. Code tit. 43, § XIII-2719