Current through Register Vol. 50, No. 9, September 20, 2024
Section XIII-2141 - Remedial Measures: Cast Iron and Ductile Iron Pipelines [49 CFR 192.489]A. General Graphitization. Each segment of cast iron or ductile iron pipe on which general graphitization is found to a degree where a fracture or any leakage might result, must be replaced. [ 49 CFR 192.489(a) ]B. Localized Graphitization. Each segment of cast iron or ductile iron pipe on which localized graphitization is found to a degree where any leakage might result, must be replaced or repaired, or sealed by internal sealing methods adequate to prevent or arrest any leakage. [ 49 CFR 192.489(b)]La. Admin. Code tit. 43, § XIII-2141
Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:237 (April 1983), amended LR 10:529 (July 1984), LR 30:1256 (June 2004).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.