Section XI-1559 - Construction Records
A. A complete record that shows the following must be maintained by the operator involved for the life of each pipeline facility:
1. the total number of girth welds and the number nondestructively tested, including the number rejected and the disposition of each rejected weld;
2. the amount, location and cover of each size of pipe installed;
3. the location of each crossing of another pipeline;
4. the location of each buried utility crossing;
5. the location of each overhead crossing;
6. the location of each valve, weighted pipe, corrosion test station, or other item connected to the pipe.