Current through Register Vol. 50, No. 9, September 20, 2024
Section V-30428 - Overpressure Safety Devices and Overfill Protection Systems [49 CFR 195.428]A. Except as provided in §30428 B, each operator shall, at intervals not exceeding 15 months, but at least once each calendar year, or in the case of pipelines used to carry highly volatile liquids, at intervals not to exceed seven and one-half months, but at least twice each calendar year, inspect and test each pressure limiting device, relief valve, pressure regulator, or other item of pressure control equipment to determine that it is functioning properly, is in good mechanical condition, and is adequate from the standpoint of capacity and reliability of operation for the service in which it is used. [ 49 CFR 195.428(a)] B. In the case of relief valves on pressure breakout tanks containing highly volatile liquids, each operator shall test each valve at intervals not exceeding five years. [ 49 CFR 195.428(b)] C. Aboveground breakout tanks that are constructed or significantly altered according to API Standard 2510 after October 2, 2000, must have an overfill protection system installed according to Section 7.1.2 of API Standard 2510. Other aboveground breakout tanks with 600 gallons (2271 liters) or more of storage capacity that are constructed or significantly altered after October 2, 2000, must have an overfill protection system installed according to API Recommended Practice 2350 (incorporated by reference, see §30107). However, operators need not comply with any part of API Recommended Practice 2350 for a particular breakout tank if the operator notes in the manual required by §30402 why compliance with that part is not necessary for safety of the tank. [ 49 CFR 195.428(c)] D. After October 2, 2000, the requirements of §30428 A and B for inspection and testing of pressure control equipment apply to the inspection and testing of overfill protection systems. [ 49 CFR 195.428(d)] La. Admin. Code tit. 33, § V-30428
Promulgated by the Department of Natural Resources, Office of Conservation, Pipeline Division, LR 29:2828 (December 2003), Amended LR 441028 (6/1/2018).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:753.