Current through Register Vol. 50, No. 9, September 20, 2024
Section V-30250 - Clearance between Pipe and Underground Structures [49 CFR 195.250]A. Any pipe installed underground must have at least 12 inches (305 millimeters) of clearance between the outside of the pipe and the extremity of any other underground structure, except that for drainage tile the minimum clearance may be less than 12 inches (305 millimeters) but not less than 2 inches (51 millimeters). However, where 12 inches (305 millimeters) of clearance is impracticable, the clearance may be reduced if adequate provisions are made for corrosion control. [ 49 CFR 195.250] La. Admin. Code tit. 33, § V-30250
Promulgated by the Department of Natural Resources, Office of Conservation, Pipeline Division, LR 29:2820 (December 2003).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:753.