Section V-30189 - Design and Construction of Above Ground Breakout Tanks [49 CFR 195.132]A. Each above ground breakout tank must be designed and constructed to withstand the internal pressure produced by the hazardous liquid to be stored therein and any anticipated external loads. [ 49 CFR 195.132(a)] B. For aboveground breakout tanks first placed in service after October 2, 2000, compliance with Subsection A. of this Section requires one of the following. [ 49 CFR 195.132(b)] 1. Shop-fabricated, vertical, cylindrical, closed top, welded steel tanks with nominal capacities of 90 to 750 barrels (14.3 to 119.2 m3) and with internal vapor space pressures that are approximately atmospheric must be designed and constructed in accordance with API Spec 12F (incorporated by reference, see §30107). [ 49 CFR 195.132(b)(1)] 2. Welded, low-pressure [i.e., internal vapor space pressure not greater than 15 psig (103.4 kPa)], carbon steel tanks that have wall shapes that can be generated by a single vertical axis of revolution must be designed and constructed in accordance with API Std 620(incorporated by reference, see §30107). [ 49 CFR 195.132(b)(2)] 3. Vertical, cylindrical, welded steel tanks with internal pressures at the tank top approximately atmospheric pressures [i.e., internal vapor space pressures not greater than 2.5 psig (17.2 kPa), or not greater than the pressure developed by the weight of the tank roof] must be designed and constructed in accordance with API Std 650 (incorporated by reference, see §30107). [ 49 CFR 195.132(b)(3)] 4. High pressure steel tanks [i.e., internal gas or vapor space pressures greater than 15 psig (103.4 kPa)] with a nominal capacity of 2000 gallons (7571 liters) or more of liquefied petroleum gas (LPG) must be designed and constructed in accordance with API Std 2510(incorporated by reference, see §30107). [ 49 CFR 195.132(b)(4)] La. Admin. Code tit. 33, § V-30189
Promulgated by the Department of Natural Resources, Office of Conservation, Pipeline Division, LR 15:629 (August 1989), amended LR 27:1526 (September 2001), amended LR 29:2817 (December 2003), Amended LR 441025 (6/1/2018).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:753.