Current through Register Vol. 50, No. 9, September 20, 2024
Section V-685 - How are time periods in the requirements in this Subchapter and my RAP computed?A. Any time period scheduled to begin on the occurrence of an act or event must begin on the day after the act or event. (For example, if your RAP specifies that you must close a staging pile within 180 days after the operating term for that staging pile expires, and the operating term expires on June 1, then June 2 counts as day one of your 180 days, and you would have to complete closure by November 28.)B. Any time period scheduled to begin before the occurrence of an act or event must be computed so that the period ends on the day before the act or event. (For example, if you are transferring ownership or operational control of your site, and wish to transfer your RAP, the new owner or operator must submit a revised RAP application no later than 90 days before the scheduled change. Therefore, if you plan to change ownership on January 1, the new owner/operator must submit the revised RAP application no later than October 3, so that the 90th day would be December 31.)C. If the final day of any time period falls on a weekend or legal holiday, the time period must be extended to the next working day. (For example, if you wish to request an administrative hearing on the administrative authority's decision to modify your RAP, then you must file your request with the secretary within 30 days after notice of the decision is served upon you. If the thirtieth day falls on Sunday, then you may submit your appeal by the Monday after. If the thirtieth day falls on July 4, then you may submit your appeal by July 5.)La. Admin. Code tit. 33, § V-685
Promulgated by the Department of Environmental Quality, Office of Environmental Assessment, Environmental Planning Division, LR 26:276 (February 2000).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:2180 et seq.