Section IX-2121 - Allowable Costs
A.Allowable costs as defined in LAC 33:IX.2105 may include, but may not be limited to, the following:
1. costs of salaries, benefits, and expendable material the applicant incurs for the project;
2. costs under construction contracts;
3. professional and consultant services;
4. facilities planning directly related to a treatment works;
5. sewer system evaluation;
6. project feasibility and engineering reports;
7. costs of complying with the National Environmental Policy Act, including costs of public notices and hearings;
8. preparation of construction drawings, specifications, estimates, and construction contract documents;
9. landscaping;
10. removal and relocation or replacement of utilities, for which the applicant is legally obligated to pay;
11. materials acquired, consumed, or expended specifically for the project;
12. a reasonable inventory of laboratory chemicals and/or other supplies necessary to initiate operation of the project;
13. start-up services for new treatment works, in accordance with guidance issued by the department;
14. project identification signs, if necessary;
15. development of a municipal pre-treatment program and purchase of monitoring equipment and construction of facilities to be used by the municipal treatment works in the pre-treatment program; and
16. costs of complying with procurement requirements.